The challenge
A substantial utilities scope, uncertain asset information and complex land and stakeholder interfaces through DCO development.
Our support
- Utility scope validation and assurance
- Programme, design and commercial management
- Statutory undertaker and land interfaces
- Advanced works and construction planning
The difference
Removed 3.9km of communications scope, approximately £1.7m, and eliminated a high-pressure gas diversion. A potential £13.9m contestable procurement saving remained an opportunity, rather than a realised saving.